Solar PV – how much shade is enough?

Google+ Pinterest LinkedIn Tumblr +

 

A group of scientists from Indiaโ€™s Aligarh Muslim University conducted a field experiment to analyse the impact of shading heaviness on voltage, current, and power on PV modules and strings.

To measure shading heaviness, the group used varying layers of shading cloth to identify a critical point, following which the value of system current and maximum power becomes insensitive to shading heaviness.

โ€œThe energy yield of a PV system can decrease during partial shading because the maximum power of the PV system can drop harshly. This paper covers a different aspect of shading, that is, shading heaviness and its impact on performance parameters,โ€ the group said. โ€œThe aim of this research is to investigate the susceptibility of the shading heaviness to a partially shaded photovoltaic system and the critical point that decreases the susceptibility of shading.โ€

The experiment was carried out on a 119 KW solar plant situated on the roof of the Aligarh Muslim University. This plant consists of 19 strings, each with 20 PV modules connected in series. The modules have a tilt angle of 27 degrees and a rated power of 315 W. Shading measurements were done on the modules of one string.

โ€œIt was observed from the datalogger recording that partial shading or changing shading heaviness has a negligible effect on the system voltage whereas current shows significant impact and hence power,โ€ the academics said. For example, on a string shaded by two layers of the cloth, the power was measured at 28.4 W, the current at 38 A, and the voltages at 245 V, while a string shaded with four layers showed 22.5 W, 23.5 A, and 243 V, respectively. An unshaded string produced 30.7 W of power, 418 A of current, and 244 V of voltage.

โ€œFrom the observed readings, we see that standard deviation up to the first four layers is significant for current and power but is insignificant for the 5th to 8th layer of shading, but for voltage, it remains insignificant for both intervals,โ€ the paper notes. โ€œShading heaviness critical point is that point where the value of system current and maximum power becomes insensitive to heaviness.โ€

According to the results, while five layers of shading cloth resulted in 17.8 W, 22 A, and 241 V, in the case of eight layers of shade, it changed to 14.7 W, 19.8 A, and 241 V. In the case of six layers, the measurements showed 16.3 W, 20.6 A, and 241 V, while in the case of seven layers, the results measured 14.9 W, 20.5 A, and 242 V.

โ€œMore experimental and simulation studies of โ€˜critical pointโ€™, the relation between shading heaviness and voltage, current and power, will be helpful in the planning and forecasting of any solar power plant,โ€ concluded the research team. โ€œIf the critical point is known, some unnecessary reconfiguration work can be reduced as the photovoltaic system becomes insusceptible to shading heaviness when the critical point is met.โ€

Their findings were presented in โ€œImpact of shading heaviness on voltage, current and power of the solar photovoltaic string,โ€ published in Next Sustainability.

Author: Lior Kahana

This article was originally published inย pv magazineย and is republished with permission.

Share.

Leave A Reply

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.