Lesotho Highlands Water Project (LHWP II) now Eight Years Delayed

  • The second phase of the Lesotho Highlands Water Project (LHWP II) should have been delivering water to Gauteng this year but it’s about eight years behind schedule reports OUTA.
  • The agreement with Lesotho means that South Africa will be paying a minimum charge for the water that was expected to be delivered, even if it doesn’t arrive before 2026.
  • The agreement also ties both countries into an arrangement that encourages substantial waste of water, even in times of drought.

The Organisation Undoing Tax Abuse (OUTA) released an updated report on the progress of the Lesotho Highland Water Project Phase II (LHWP II). This follows a number of actions by OUTA since 2017 to apply pressure on authorities over the delays of this critical project which is responsible for Gauteng’s water security.

“We have seen good progress since 2017 but there is a lot of work to be done, especially because the LHWP II was supposed to start supplying Gauteng with water this year but instead we are seeing water constraints in our metros,” says Julius Kleynhans, Operations Executive at OUTA. “We believe that those in the new administration have played a significant role in encouraging progress in this project.”

LHWP II is late

The LHWP Phase II was supposed to have started delivering the extra water to Gauteng this year.

LHWP II involves building the new Polihali Dam, the Kobong Dam, the Kobong pumped storage power station and transfer tunnels into the existing Katse Dam. The main construction contracts have not yet been awarded.

LHWP I was completed in January 1996 and has been delivering water from the massive Katse Dam in Lesotho through 82km of tunnels across the South African border to an outfall in the Ash River near Clarens in the Free State since 1998.

From there the water runs down rivers into the Vaal Dam, where it is used to supply the increasingly thirsty Gauteng and assist in the dilution of pollutants such as acid mine drainage.

Read more Water-related news and insight here

South Africa and Lesotho built it jointly

The new delivery date for the extra water through LHWP II is now early 2026.

However, based on the current progress in the awarding of tenders and applying realistic timelines for such a complex project, OUTA is of the opinion that the first water will not be delivered before late 2026 or early 2027.

This will be about eight years later than originally planned and escalate the project costs by billions, and taxpayers and Gauteng water-users will have to cough up for this.

LHWP encourages the waste of water

South Africa pays Lesotho billions of rand in water royalties. Lesotho also uses the scheme to generate electricity from the 72MW Muela hydropower station downstream from Katse.

It’s supposed to benefit both parties.

But the current rule for the operation of Katse Dam is to continuously release water via the transfer tunnel between Muela hydropower station and the Ash River outfall. This was agreed to allow Lesotho to generate the maximum amount of electricity, but this is not optimal from a water-management perspective because it compromises water security.

This year a dry season and the continuous flow left the Katse Dam at 17% by September, when the tunnels were closed for two months of planned maintenance.

Earlier this year, the Vaal Dam was overflowing but water still ran into it from Katse – and through it and on downstream to the Atlantic Ocean. Rand Water’s website update on dam levels this week shows Katse still at 17% and Vaal Dam at 43%. Mohale Dam, which feeds Katse, is at 27%.

Although the Katse tunnel to South Africa is due to reopen, it’s not going to help fill the Vaal yet.

The contract is based on payment for a minimum amount of water, regardless of what is delivered. These amounts are due to increase sharply this year because LHWP II was due to come online this year. So South Africa will be paying even if we wait until 2026 for the increased supply.

Now there’s a plan to send Katse water to Botswana

South Africa, Lesotho and Botswana have apparently agreed to build a 720km pipeline from Katse across South Africa to supply water to Botswana. This is the Lesotho-Botswana Water Transfer Project.

To date, there has been no public participation in this scheme or a formal international agreement for the project. We understand that feasibility studies are underway. “We’d like to know more and would like the public to have their say about this,” says OUTA.

OUTA is of the opinion that such a project should not be on the cards as South Africa already lacks sufficient water supplies with the increased demands in population growth, urbanisation, economic demands and food security.

Some good news

At least 36 of the main contracts on LHWP II have been signed, although the big construction contracts are still awaited.

After disastrous corruption in LHWP II (the then CEO of the Lesotho Highlands Development Authority, which runs the Lesotho end of the project, spent nine years in jail), the LHWP II has anti-corruption protocols written into it.

Nomvula Mokonyane is now out of the picture. Mokonyane was Minister of Water and Sanitation from May 2009 until April 2014 and has been strongly linked to state capture in South Africa. She reportedly tried to force the appointment on LHWP II of an engineering firm without acknowledgement of the required skills, experience and established procedures, but didn’t succeed.

Mokonyane and her successor, Gugile Nkwinti, who was the minister until April 2019, were South Africa’s political representatives on a scheme that has seen years of delays.

There are still questions over corruption and mismanagement

The Project Management Unit was appointed in 2013 but still hasn’t been given the appropriate decision-making powers. OUTA questions why this unit is being bypassed.

There’s no independent water regulator in South Africa to watch over tariffs that the public is ultimately charged for this water.

The delays – at least some blamed on Mokonyane’s meddling – may have cost an extra R1 billion, states OUTA.

Author: Nicolette Pombo-van Zyl

This article was originally published on ESI Africa and is republished with permission with minor editorial changes.

 

Hansgrohe Tap Mixer

Clean drinking water is becoming increasingly scarce. Do your bit to save water. You can start by retrofitting your tap and shower mixers at home with Hansgrohe EcoSmart technology.

Visit the Hansgrohe Showroom in Johannesburg to see the Rainfinity range in action.

Find a Hansgrohe Retail Store near you . Hansgrohe is present in South Africa, Madagascar, Nigeria, Kenya, Botswana, Seychelles, Mauritius, Namibia, Tanzania, Zimbabwe, Ghana and Zambia.

About Author

Green Building Africa promotes the need for net carbon zero buildings and cities in Africa. We are fiercely independent and encourage outlying thinkers to contribute to the #netcarbonzero movement. Climate change is upon us and now is the time to react in a more diverse and broader approach to sustainability in the built environment. We challenge architects, property developers, urban planners, renewable energy professionals and green building specialists. We also challenge the funding houses and regulators and the role they play in facilitating investment into green projects. Lastly, we explore and investigate new technology and real-time data to speed up the journey in realising a net carbon zero environment for our children.

Copyright Green Building Africa 2024.